Aramco – Sinopec

Project Description: Sinopec Project – PKG-17 (KM 132 DDS)

This project involved the execution of a Directional Drilling System (DDS) / Horizontal Directional Drilling (HDD) scope under Sinopec Project PKG-17 in Saudi Arabia, delivered for ARAMCO.

The scope of work included the installation of a 12-inch steel pipeline using HDD methodology over a drilling length of 150 meters, forming part of a larger 132-kilometer pipeline package. The HDD operation was carried out in soft ground conditions, requiring controlled drilling, bore stability management, and precise alignment to meet engineering and safety standards.

All activities were executed in strict compliance with project specifications, quality requirements, and environmental guidelines, ensuring seamless integration with the overall pipeline network. The project commenced in January 2023 and was completed in alignment with client and contractor expectations.

Project Start: January 2023
Execution Method: HDD / DDS
Pipe Specification: 12” Steel Pipe
HDD Length: 150 meters
Ground Conditions: Soft Ground
Client: ARAMCO

This project highlights proven capability in short-to-medium length HDD crossings, oil & gas pipeline installations, and execution under demanding site and ground conditions within Saudi Arabia.

Project Gallery

Specifications

Pipeline Diameter: 12 inches

A 12-inch diameter pipeline was selected to meet project flow requirements while ensuring structural integrity and long-term operational reliability.

High-grade carbon steel pipe was used to provide durability, pressure resistance, and compliance with oil and gas industry standards.

The HDD crossing covered a total drilled length of 150 meters, executed with controlled drilling parameters to maintain accuracy and bore stability throughout the operation.

The HDD crossing formed part of a larger 132-kilometer pipeline package, contributing to the overall network connectivity and infrastructure development.

The project was executed in soft ground conditions, requiring careful drilling fluid management and bore support techniques to prevent collapse and ensure smooth pipe installation.

A straight, survey-controlled bore profile was maintained in accordance with the approved engineering alignment to ensure accurate entry and exit positioning.

The installation was carried out through a sequential HDD process consisting of pilot hole drilling, progressive reaming to the required diameter, and final pipe pull-back.

Project Information

Sinopec Project PKG-17 KM 132 DDS

12" Pipe Size km 132

PROJECT BY

ARAMCO

METHOD

HDD

PIPE DIAMETER

12" steel pipe

LENGTH (M)

150